Greenfield Avenue Culvert over Lehr Ditch
PROJECT: Greenfield Avenue Culvert over Lehr Ditch
TIMELINE: Construction began March 22, 2021. Greenfield Avenue was reopened to traffic on April 10, 2021.
PROJECT GOALS: Reconstructing a deficient water culvert.
OWNER: City of Noblesville
ENGINEER: Beam, Longest & Neff
CONTRACTOR: 3D Company
SCOPE: Remove and replace the current culvert over Lehr Ditch. Work will close Greenfield Avenue between Follow Drive and Marilyn Road.
ROAD CLOSURE:21-day closure from March 22 to April 9, 2021. Detour route includes: Union Chapel Road, 146th Street and Boden Road. To view the detour map, click here.
MILEAGE: 0.05 miles
ESTIMATED COST: $700,000
COUNCIL DISTRICT: 6 (Megan Wiles)