Greenfield Avenue Culvert over Lehr Ditch

Greenfield

PROJECT: Greenfield Avenue Culvert over Lehr Ditch

TIMELINE: Construction began March 22, 2021. Greenfield Avenue was reopened to traffic on April 10, 2021.

PROJECT GOALS: Reconstructing a deficient water culvert.

OWNER: City of Noblesville

ENGINEER: Beam, Longest & Neff

CONTRACTOR: 3D Company

SCOPE: Remove and replace the current culvert over Lehr Ditch. Work will close Greenfield Avenue between Follow Drive and Marilyn Road.

ROAD CLOSURE:21-day closure from March 22 to April 9, 2021. Detour route includes: Union Chapel Road, 146th Street and Boden Road. To view the detour map, click here.

MILEAGE: 0.05 miles

ESTIMATED COST: $700,000

    COUNCIL DISTRICT: 6 (Megan Wiles)