Little Chicago Road Lift Station (LS9) Upgrade

Lift Station 9

PROJECT: Little Chicago Road Lift Station (LS9) Upgrade

TIMELINE: Construction began in 2023. It's construction is in coordination with the Little Chicago Road Pedestrian Bridge.

PROJECT GOALS: The lift station was installed in the early 1970s and is beyond its life expectancy and is in need of replacement.

OWNER: City of Noblesville

ENGINEER: HNTB

CONTRACTOR: Not awarded

SCOPE: A new lift station is to be constructed immediately north of the existing lift station. The old lift station will be decommissioned and removed once the new station is activated. 

LOCATION: Northeast corner of Little Chicago Road and Hawthorne Place.

ESTIMATED COST: $1,275,000

    COUNCIL DISTRICT: 1 (Mike Davis)

    Timeline