Greenfield Avenue over Wheeler & Wheeler
PROJECT: Greenfield Avenue over Wheeler & Wheeler
TIMELINE: Utility relocation started in 2024 and continues through February 2025. Construction is tentatively expected to start in March 2025.
ROAD CLOSURE: A 30-day closure of Greenfield Avenue is needed for this project.
PROJECT GOALS: Replacing a culvert under Greenfield Avenue and improve the intersection of Greenfield Avenue and Arbor Grove Boulevard.
OWNER: City of Noblesville
ENGINEER: WSP
CONTRACTOR: Midwest Paving
SCOPE: Repair culvert under Greenfield Avenue and widen intersection and improve mobility and safety at Arbor Grove subdivision entrance.
MILEAGE: 0.25 miles
ESTIMATED COST: $579,000
COUNCIL DISTRICT: 5 (Dave Johnson) and 6 (Megan Wiles)