Lift Station 8 Replacement (Oakbay)
PROJECT: Lift Station 8 Replacement (Oakbay)
TIMELINE: Construction is expected to take place from June to August 2025.
PROJECT GOALS: Replacing the existing Lift Station 8, located on Lands End Circle in Oakbay, with new pumps to increase flow limitations. Placing a prefabricated building to house the lift station to help the lift station blend in with the neighborhood. The prefabricated building will match surrounding homes.
OWNER: Noblesville Utilities
ENGINEER: Jones & Henry
CONTRACTOR: Bynum Fanyo
SCOPE: Retrofit existing wet well, replace pumps and controls, and place prefabricated lift station building.
ESTIMATED COST: $576,163.00
COUNCIL DISTRICT: 1 (Mike Davis)